  • Project conceived in 1991
  • Tatas-led consortium walks out over delay in clearance
  • May 1999: MoU signed betwen KSIIDC and Airport Authority of India
  • June 1999: Expression of interest invited
  • November 8, 2000: Bidders asked to submit detailed project report
  • October 29, 2001: Seimen’s led consortium selected by Government of Karnataka
  • Jan 23, 2002: Shareholders agreement signed
  • Jan 2002: Ex-PM Vajpayee performed ground breaking
  • Stake holders meeting held in Jan 2003
  • Ex-CM SM Krishna performed ground breaking [again!] in Jan 2004
  • July 2004: Concession agreement signed between State Govt., Govt of India and BIAL
  • NOC [No Objection Certificate] pending from Defence Ministry
  • Dec 21, 2004: Final clearance given by Dharam Singh govt
  • Jan 20, 2005: State support agreement between State Govt and BIAL
  • Jan 20, 2005: Land lease agreement between State Govt and BIAL
  • March 11, 2005: EPC contracts with Seimens (Germany and India) and L&T
  • April 8, 2005: Operation and maintenance agreement – BIAL & Unique Zurich
  • April 6, 2005: CNS/ATM agreement between BIAL and AAI
  • April 30, 2005: Land lease deed signed BIAL and KSIIDC
  • June 10, 2005: Extension of shareholders’ agreement
  • June 22, 2005: SBI guarantee to state support of Rs 350 crore
  • June 23, 2005: Declaration of financial closure by ICICI Bank
  • July 2, 2005: Construction commencement date
  • March 7, 2008: First test flight from Bangalore HAL airport to BIAL

As of June 2007 some details of the existing Bangalore HAL domestic airport are as follows,

  • 3rd busiest airport in India
  • 7.5 million passengers a year
  • Rs 100-150 crore in landing parking fees
  • 830 domestic flights per week
  • 29 nonstop flights per week